Project: INTO Halls of Residence, University of Exeter
Client: INTO Value: £20m Contract: JCT 1998 Design & Build Duration: 80 Weeks Client Brief: INTO specialise in providing teaching and residential solutions for international students on university campuses across the world. The project is designed to achieve BREEAM ‘very Good’ rating. the first phase of the contract for 187 beds was completed in December 2010 with the remainder following in April 2011. The considerate constructors monitor’s reports scored this project very highly at 37 points out of a possible 40. |
|
|